CR 129

Location: CR 129 from south of Brushy Creek to north of the southern Williamson County Line

Description: The project will adjust roadway elevation to address sight-distance issues. Williamson County will maintain two lanes in the project area, reconstructing the existing 10-foot lanes as 11-foot lanes and adding two-foot shoulders. The project is being completed as part of the voter-approved 2019 Road Bond.

Status: Design was completed by Garver. Right-of-way appraisals and acquisition are complete and utility coordination is underway. Construction is expected to begin in fall 2023 and be complete in early 2024. View a project fact sheet (PDF).

Contact: Email the Roads Department or phone 512-943-1195.