Location: From CMTA Railroad to CR 201
Description: CR 200 is being reconstructed to a two-lane roadway with a center turn lane and shoulders (3 lanes of an ultimate six-lane roadway) from CMTA Railroad to CR 201. The improvements include the reconstruction of the existing roadway, performing grading and drainage improvements, placing flexible base, hot mix asphalt pavement and installing striping and pavement markers.
Status: MA Smith Contracting is the contractor. A groundbreaking ceremony was held on October 27, 2021. Construction began November 15, 2021, and will be completed in fall 2022. A ribbon-cutting ceremony was held on Wednesday, October 19.
Contact: Email the Roads Department or phone 512-260-4280